Project Background:
This storm outfall and trail restoration project is in the community of Mount Albert, adjacent to Vivian Creek Park. There are four storm outfalls and one span of trail in need of repair. Town staff have investigated and continue to monitor the condition of the outfalls, although they require repair, the current state is stable and interim holding repairs will be completed (if necessary) until construction takes place. Similarly, the slope behind 13 and 15 Valley Mills Road was also inspected, monitored, and deemed stable.
Vivian Creek Trail Feedback
Thank you to everyone who completed the Vivian Creek Trail Closure survey. Your thoughts and feedback have been incorporated into a staff memo for Council. The memo was presented to Committee of the Whole on July 25, 2023, to view the Agenda, please visit the Council meeting portal.
Storm Outfall Locations:
- 66 Alice Street (rear-lot)
- 68 and 70 Alice Street (rear-lot)
- Behind 15 and 17 Valley Mills Road (Two Storm Outfalls)
Trail Restoration Location:
- Behind 13 and 15 Valley Mills Road
The map below outlines the trail and storm outfall locations. This project has several complex
factors that are being considered as part of the repairs, including slope stability, erosion, construction access, environmental and trail impacts. With the help of preliminary input received by external construction and engineering professionals, Town staff have awarded the design contract to Aquafor Beech.
Next Steps:
- Continue to monitor the outfall locations.
- Complete interim repairs, if required until the construction can be completed.
- Construction funding for Outfalls 1-4 was approved as part of the 2026 Capital Budget Deliberations, the construction contract is expected to be awarded in the summer of 2026.
- Details about construction phasing and duration for Outfalls 1-4 will be confirmed once the construction contract is awarded.
- Construction funding for the Trail Restoration is expected to be requested as part of the 2027 Capital Budget Deliberations.
Public Engagement:
- A Public Information Centre (PIC) took place on Monday October 6th, 2025 from 5 to 8pm, at the Mount Albert Community Centre (53 Main Street, Mount Albert). Thank you to everyone who was able to join us.
Project Notices:
Council Reports and Memos: