Building Permit Stage:
This stage is when builders apply for each building permit, allowing for homes and other structures to be built.
Maintenance Stage:
In this stage, construction is finished, and the subdivision is complete. The Town will officially issue the start of Maintenance once the Developer has reached all requirements of their Agreement.
In this municipality, the subdivision must remain in the maintenance period for a minimum of 13 months. During the maintenance period, various construction activities may still occur to satisfy the Developer’s agreement with the Town and prepare the subdivision for assumption.
After 13 months, the developer is eligible to apply for assumption.
Please note: Assumption has no time limit and is based on the Developer meeting all requirements of their agreement with the Town. The Developer maintains responsibility for the infrastructure in the subdivision until the maintenance period is complete.
Assumption Stage:
Once the maintenance period has passed and all deficiencies have been corrected, the Town will assume full responsibility for the maintenance of all municipal services.