Yonge Street is currently closed in both directions between the Dutch Settlers Square Plaza entrance and Dutch Settlers Court. Rolling closures will occur between Olive Street and Dutch Settlers Court. Access to local businesses and community facilities will be maintained via signed detour routes. All pedestrian access, including the multi-use pathway, will be rerouted. Pedestrians can also follow signed detour routes.
Current Project Status 
The Enhance EG Yonge Street Revitalization project is transitioning to a single phase, scheduled for completion by late August 2026. For the remainder of the project traffic controls will remain in place. Road closures will take place throughout the project as needed. Signage will be in place to guide travellers.
Local access to all properties within the work zone, including homes and businesses, the Holland Landing Fire Station and the Holland Landing Community Centre and Library, will be maintained during construction.
Thank you for your patience and cooperation as these important infrastructure improvements are completed.
What is being worked on this week:
- Installation of Services to 19449 Yonge Street. Residents can expect open excavation on Yonge Street just south of Thompson Drive
- Culvert and pedestrian bridge replacement is on-going road, closed between Dutch Settlers Plaza and Dutch Settlers Court
- Asphalt restoration
For weekly project history, please contact the project team.
What is the Holland Landing Yonge Street Revitalization project?
The Enhance EG – Holland Landing Yonge Street Revitalization Project will renew and elevate the Holland Landing Yonge Street area through improved accessibility, enhanced safety and lighting, upgraded parking and landscaping, road resurfacing, and sustainable environmental improvements. The project area focuses on Yonge Street from Mount Albert Road to Doane Road.
The Revitalization Project will include:

- Construction of a multi-use path and road resurfacing
- Upgrades to sidewalks to fill in missing links, improve connectivity and accessibility
- Public realm improvements including decorative streetlighting, streetscape, amenities, etc.
- Sidewalk connections to adjacent trail network (where applicable)
A portion of this project will also focus on the economic development opportunities of upgrading these areas. Additional projects and funding may be available for local businesses as this aspect develops and the project progresses.
Contact the project team
Business Support 
Businesses remain open during construction. Residents and visitors are encouraged to continue supporting our local businesses throughout the revitalization period. Explore local businesses through the EG Loves Local website– Downtown Holland Landing Business Directory
Businesses located within the project area have access to free, one-on-one support from the Town’s Economic Development team. This includes mentorship, marketing guidance, and connections to other programs to help you navigate this transition. A comprehensive list of local business support partners can be found here.
If you’re interested in mentorship opportunities, business resources, or would like tailored support for your business, please email ecdev@eastgwillimbury.ca
Advantage EG Website
Project Milestones and Accomplishments
Work completed on the project so far includes:
- Watermain replacement including hydrants
- Utility relocations
- Storm sewer replacement (near completion)